SMC Bathroom Ceiling Panels
Installation
- 01
- Take a measurement (a shorter side : 2 points or more, a longer side : 3 points or more)
- 02
- Check dimension.
- 03
- Locate the body of ceiling panel at the center of a construction place
- 04
- A ventilation fan is located at the center of side panel at a bathtub or shower booth.
- 05
- Install in such an order as : Side flat panel => Body => Side flat panel
- 06
- In a joint area where panels meet, construct the Vis RIB fixation in an internal of evey 30cm.
When constructing, take heed of a size error at the folding area.
- 07
- After checking whether there is any chasm between a ceiling panel and a tile, make a silicon treatment.
- 08
- Wipe out stains.
Note
-
- 01
- Check 150mm between the upper line of a tile and the lower part of pipe.
- 02
- Check the upper line of a tile/doorframe/window frame.
(A tile should be the uppermost)
- 03
- Remove mortar on the top
-